Assigned:
Friday, March 29, 2019
Due:
Friday, April 5, 2019
General Instructions
- Please review the
course information.
- You must write down with whom you worked on the assignment. If this
changes from problem to problem, then you should write down this
information separately with each problem.
- Numbered problems are all from the textbook Scheduling:
Theory, Algorithms and Systems.
Problems
- Consider a Q|pmtn|ΣCj problem where the machine speeds are (4,2,2,1) and the processing times are (4,8,18,19,21,32,42). Show the optimal schedule.
- Consider the project scheduling problem given in the notes, where we were interested
in the time-cost tradeoff. Start where the example in class ended, and run three more iterations, showing the cheapest way to decrease the project length by one time unit each time.
- Problem 6.1
- Problem 6.2
- Problem 6.12