Assigned:
Friday, February 22, 2019
Due:
Friday, March 1, 2019
General Instructions
- Please review the
course information.
- You must write down with whom you worked on the assignment. If this
changes from problem to problem, then you should write down this
information separately with each problem.
- Numbered problems are all from the textbook Scheduling:
Theory, Algorithms and Systems.
Problems
- Problem 3.23.
- Problem 5.1.
- Consider P||Cmax. Give an example of a set of jobs and machines such that list scheduling (you choose the order
of the list) gives a schedule that is close to 2 times the lower bound.
- Consider P|rj, prec|Cmax. Show that the greedy algorithm is a 2-approximation.
- Start thinking about who will be in your project group and what you will work on (no need to turn anything in this week).
Switch to: